Palm Jebel Ali is about a quarter built, by its developer's own board

A fan of terracotta paper fronds on a warm sand ground, the nearest quarter of each filled in solid and the rest left as outline

Every large Dubai project is described twice: once in launches and once in percentages. Nakheel publishes the second kind for Palm Jebel Ali, and it is the more useful number.

The headline figure

26.75% overall progress, as of March 2026.

By frond

Frond O leads at 37.44%, followed by N at 29.20%, K at 27.71%, L at 24.71%, M at 22.10% and P at 20.50%.

By trade, which is the more revealing cut

Substructure 93.27%. Superstructure 68.40%. Infrastructure 65.05%. Building work 21.64%. MEP 18.76%.

What that shape means

Foundations are all but finished and frames are well advanced, while the trades that turn a frame into a house — finishes and building services — are only about a fifth done. That is the normal order of construction, and it is also the reason an island that looks structurally complete from the water is still years from occupation.

Read the trade breakdown rather than the overall percentage, because the two tell different stories about time. Substructure at 93% and MEP at 19% is not a project four months from finishing; it is a project that has done the fast, heavy work and has yet to do the slow, labour-intensive part, and finishing trades are where Dubai schedules most often slip. The frond numbers are worth checking against whichever frond a particular unit sits on — a 17-point spread between Frond O and Frond P is more than a rounding difference. Note the date too: these figures are Nakheel's own and were current in March, so they understate where the island stands now by roughly two quarters of work.

Source: Nakheel checked against the source